Installing a Construction Safety Screen

  • Install guide rails or anchor plates as per the engineer’s drawings before lifting the screen into position.

  • Use a mobile crane or tower crane to lift the safety screen using certified lifting points.

  • Align the screen with the edge protection tracks or embedded anchors on the structure.

  • Engage locking mechanisms and secure the screen to the structure at all anchor points.

  • Use taglines to control sway during lifting and ensure safe alignment at height.

  • Each screen section must be inspected and signed off before the platform is handed over.

Safety Tips & Best Practices

  • Follow only engineered drawings and installation sequences approved through the temporary works coordinator.

  • Ensure lifting configuration matches approved lift plan, including certified chains and shackles.

  • Taglines must be used at all times to maintain control during positioning.

  • All operatives must wear full fall protection when working near exposed edges.

  • Check all welds, connections, and locking pins before and after each lift.

  • Inspect screens for any damage or deformation prior to lifting or reinstallation.

  • Maintain clear exclusion zones below during all hoisting operations.

  • Screens must not be moved or adjusted without authorisation from the temporary works supervisor.

⚠️ Disclaimer

The installation method illustrated or described is for guidance only.
All lifting and fixing operations must follow your project-specific Lift Plan and Temporary Works Design.
Work must be supervised by a Competent Person, in line with LOLER, PUWER, and relevant UK construction standards.