Lifting & Installation Procedure – CantiDeck

  • Pre-Lift Inspection

  • Inspect the platform frame, certified lifting points, and handrails for any signs of damage, wear, or corrosion.

  • Ensure gates are closed and secured with a bolt or padlock.

  • Clear any debris from the deck and underside before lifting.

  • Attach Lifting Chains

  • Connect all four legs of the chain sling to the certified lifting points.

  • Confirm lifting gear is correctly rated, in good condition, and free from twists or kinks.

  • Secure any unused chain legs back to the master link.

  • Initial Lift & Balance Check

  • Raise the platform slightly to check load balance and sling tension across all lifting points.

  • Stop immediately if the load tilts or shows instability.

Safety Tips & Best Practices – CantiDeck

  • Inspect Before Use

  • Check lifting points, handrails, gates, and fixings for wear or defects.

  • Verify all bolts are tight and screw jacks are in place before installation.

  • Use Correct Lifting Gear

  • Only use certified four-leg chains rated for the platform’s WLL.

  • Do not use damaged, kinked, or untested lifting gear.

  • Communication During Lifting

  • Slingers and banksmen must remain in constant communication via radios or agreed hand signals.

  • One designated signaller must give instructions to the crane operator.

  • Keep Clear During Lifting

  • Never stand under or close to the load while it is being lifted or lowered.

  • Use taglines to control swing and prevent uncontrolled movement.

  • Maintain exclusion zones at both ground level and the installation floor.

  • Securing After Placement

  • Ensure legs are tied to the ceiling and screw jacks tightened.

  • Check that the deck is level, plumb, and secure before releasing the chains.

  • Only trained operatives wearing harnesses may complete installation inside the building.

⚠️ Disclaimer

This lifting and installation procedure for CantiDeck platforms is provided for guidance only.
All operations must strictly follow the site-specific Lift Plan and method statement.
Lifting accessories, platform components, and associated equipment must be inspected and confirmed suitable prior to use.
All lifting activities must be supervised by a Competent Person and carried out in accordance with LOLER, PUWER, BS 7121, and applicable UK construction standards.
Only trained and authorised operatives may assemble, install, or use the platform.
Failure to follow these guidelines may result in serious injury, equipment damage, or unsafe installation.